The studied facility is a nine-story office building with a total floor area of 71,500 square feet. The building receives both steam and chilled water from an energy company while hot water is generated through steam-water heat exchangers in the building. The interior zones from the 4th floor to the 9th floor is initially served by one constant volume (CV) air handling unit (AHU) system with electrical reheats at each terminal box while the exterior zones is initially served by a constant volume primary AHU system with a 2-pipe hot water/ chilled water induction unit system. The low levels of the building are served by one constant volume AHU system with electrical reheats at each terminal box. The excessive fan power and electrical reheat, chilled water was used in the building. Continuous Commissioning (CC™) was applied to solve existing facility problems, to optimize facility operation, and to reduce operational costs. The CCTM measures include AHU variable air volume (VAV) conversion, AHU economizer optimal control, integrated AHU fan speed and supply air temperature control, integrated operation between interior zone and exterior AHUs, chilled water system return temperature optimal control. This paper presents detailed CC™ measures and results of this integrated system optimization study.

Original languageEnglish
Title of host publicationWorld Energy Engineering Congress, WEEC 2008
Pages2105-2113
Number of pages9
Volume4
StatePublished - Dec 1 2008
Externally publishedYes
EventWorld Energy Engineering Congress, WEEC 2008 - Washington, DC, United States
Duration: Oct 1 2008Oct 3 2008

Other

OtherWorld Energy Engineering Congress, WEEC 2008
CountryUnited States
CityWashington, DC
Period10/1/0810/3/08

Fingerprint

Air
Water
Fans
Steam
Economizers
Integrated control
Office buildings
Temperature control
Heat exchangers
Pipe
Costs
Industry
Temperature

ASJC Scopus subject areas

  • Energy Engineering and Power Technology
  • Fuel Technology

Cite this

Xu, K., Wang, G., Wang, Z., & Liu, M. (2008). Integrated system optimization through Continuous Commissioning: A case study. In World Energy Engineering Congress, WEEC 2008 (Vol. 4, pp. 2105-2113)

Integrated system optimization through Continuous Commissioning : A case study. / Xu, Ke; Wang, Gang; Wang, Zhan; Liu, Mingsheng.

World Energy Engineering Congress, WEEC 2008. Vol. 4 2008. p. 2105-2113.

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Xu, K, Wang, G, Wang, Z & Liu, M 2008, Integrated system optimization through Continuous Commissioning: A case study. in World Energy Engineering Congress, WEEC 2008. vol. 4, pp. 2105-2113, World Energy Engineering Congress, WEEC 2008, Washington, DC, United States, 10/1/08.
Xu K, Wang G, Wang Z, Liu M. Integrated system optimization through Continuous Commissioning: A case study. In World Energy Engineering Congress, WEEC 2008. Vol. 4. 2008. p. 2105-2113
Xu, Ke ; Wang, Gang ; Wang, Zhan ; Liu, Mingsheng. / Integrated system optimization through Continuous Commissioning : A case study. World Energy Engineering Congress, WEEC 2008. Vol. 4 2008. pp. 2105-2113
@inproceedings{f26fb9b359744dd29f06c004b7dc6ae7,
title = "Integrated system optimization through Continuous Commissioning: A case study",
abstract = "The studied facility is a nine-story office building with a total floor area of 71,500 square feet. The building receives both steam and chilled water from an energy company while hot water is generated through steam-water heat exchangers in the building. The interior zones from the 4th floor to the 9th floor is initially served by one constant volume (CV) air handling unit (AHU) system with electrical reheats at each terminal box while the exterior zones is initially served by a constant volume primary AHU system with a 2-pipe hot water/ chilled water induction unit system. The low levels of the building are served by one constant volume AHU system with electrical reheats at each terminal box. The excessive fan power and electrical reheat, chilled water was used in the building. Continuous Commissioning (CC™) was applied to solve existing facility problems, to optimize facility operation, and to reduce operational costs. The CCTM measures include AHU variable air volume (VAV) conversion, AHU economizer optimal control, integrated AHU fan speed and supply air temperature control, integrated operation between interior zone and exterior AHUs, chilled water system return temperature optimal control. This paper presents detailed CC™ measures and results of this integrated system optimization study.",
author = "Ke Xu and Gang Wang and Zhan Wang and Mingsheng Liu",
year = "2008",
month = "12",
day = "1",
language = "English",
isbn = "9781605607115",
volume = "4",
pages = "2105--2113",
booktitle = "World Energy Engineering Congress, WEEC 2008",

}

TY - GEN

T1 - Integrated system optimization through Continuous Commissioning

T2 - A case study

AU - Xu, Ke

AU - Wang, Gang

AU - Wang, Zhan

AU - Liu, Mingsheng

PY - 2008/12/1

Y1 - 2008/12/1

N2 - The studied facility is a nine-story office building with a total floor area of 71,500 square feet. The building receives both steam and chilled water from an energy company while hot water is generated through steam-water heat exchangers in the building. The interior zones from the 4th floor to the 9th floor is initially served by one constant volume (CV) air handling unit (AHU) system with electrical reheats at each terminal box while the exterior zones is initially served by a constant volume primary AHU system with a 2-pipe hot water/ chilled water induction unit system. The low levels of the building are served by one constant volume AHU system with electrical reheats at each terminal box. The excessive fan power and electrical reheat, chilled water was used in the building. Continuous Commissioning (CC™) was applied to solve existing facility problems, to optimize facility operation, and to reduce operational costs. The CCTM measures include AHU variable air volume (VAV) conversion, AHU economizer optimal control, integrated AHU fan speed and supply air temperature control, integrated operation between interior zone and exterior AHUs, chilled water system return temperature optimal control. This paper presents detailed CC™ measures and results of this integrated system optimization study.

AB - The studied facility is a nine-story office building with a total floor area of 71,500 square feet. The building receives both steam and chilled water from an energy company while hot water is generated through steam-water heat exchangers in the building. The interior zones from the 4th floor to the 9th floor is initially served by one constant volume (CV) air handling unit (AHU) system with electrical reheats at each terminal box while the exterior zones is initially served by a constant volume primary AHU system with a 2-pipe hot water/ chilled water induction unit system. The low levels of the building are served by one constant volume AHU system with electrical reheats at each terminal box. The excessive fan power and electrical reheat, chilled water was used in the building. Continuous Commissioning (CC™) was applied to solve existing facility problems, to optimize facility operation, and to reduce operational costs. The CCTM measures include AHU variable air volume (VAV) conversion, AHU economizer optimal control, integrated AHU fan speed and supply air temperature control, integrated operation between interior zone and exterior AHUs, chilled water system return temperature optimal control. This paper presents detailed CC™ measures and results of this integrated system optimization study.

UR - http://www.scopus.com/inward/record.url?scp=84865767066&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84865767066&partnerID=8YFLogxK

M3 - Conference contribution

AN - SCOPUS:84865767066

SN - 9781605607115

VL - 4

SP - 2105

EP - 2113

BT - World Energy Engineering Congress, WEEC 2008

ER -